Mike Baird's 2014 timetable for Sydney's North West rail services holds
“Services on the North West Rail Link will start in the first half of 2019”
BThe context
Baird announced the operations contract for the North West Rail Link with a first-half-2019 service start. The project combined new stations and upgraded existing ones with automated trains. Other commitments about service frequency and reliability appeared in the announcement, but this verdict grades only the opening timetable. 1
Sydney Metro's 2018–19 annual report records the North West Line opening to passengers on May 26, 2019. That date meets the stated window. It does not by itself establish that every cost, operating or customer-service commitment was also achieved. 2
Why it sounded unlikely at the time. This was a deadline set nearly five years ahead for an automated railway combining newly built and upgraded infrastructure. The public opening remained inside the announced half-year window. 1 2
CWhat actually happened
DThe receipts
- 1Sydney Metro: September 2014 operations contract announcementOriginal report · sydneymetro.info
- 2Sydney Metro: 2018–19 annual report and opening dateOutcome evidence · sydneymetro.info
We quote short excerpts and link to sources. Archived copies and screenshots, when added, are labelled separately from original publications.
EFinal verdict
Surprisingly Right
No shame score. This one came true.
FReader discussion
Comments on case 000586
Discuss the evidence. Keep it civil. No threats or personal information.Which milestones make a fair test of a multiyear transport promise?
Loading comments.