CASE #000521 · BUSINESS
Prediction Failed

Boeing says eighteen KC-46 tankers remain on track for 2017

“We remain on track to deliver the initial 18 KC-46A tankers by 2017.”

Maureen Dougherty, Boeing vice president and KC-46 tanker programme manager · October 22, 2013 · Company release announcing assembly of a third test aircraft

BThe context

Dougherty's statement came as Boeing assembled test aircraft and described progress toward the programme's delivery commitments. The release separately discussed test flights and production. Delivering eighteen tankers was a different milestone from building airframes that still required certification or modifications. 1

GAO's 2019 review reported first Air Force acceptance in January 2019 and reiterated the original August 2017 requirement for eighteen fully capable aircraft. It also documented deficiencies in aircraft that were being accepted. The missed schedule is clear even before separately assessing whether delivered equipment met every operational requirement. 2

CWhat actually happened

  1. Boeing says the initial eighteen tankers are on track for 2017. Source 1
  2. The original requirement called for eighteen fully capable aircraft. Source 2
  3. The Air Force accepts the first KC-46. Source 2

DThe receipts

  1. 1Boeing: October 2013 KC-46 production and delivery statementOriginal report · boeing.mediaroom.com
  2. 2GAO: 2019 KC-46 delivery and deficiency reviewOutcome evidence · gao.gov

We quote short excerpts and link to sources. Archived copies and screenshots, when added, are labelled separately from original publications.

EFinal verdict

Prediction Failed

90/ 100 shame score
Confidence4
Contradiction5
Significance4
Evidence5

How we score · Request a correction

FReader discussion

Comments on case 000521

Discuss the evidence. Keep it civil. No threats or personal information.
Discussion question

Should procurement scorecards separate assembly, delivery, acceptance and full operational capability?

Loading comments.

There is always another take

Surprise me again
Remind me

Download and add the reminder to your calendar. It is set for 9 a.m. in your calendar’s local time; the site does not send a reminder email.

Keep the receipts coming

New takes. In your inbox.

Sign up for new entries and updates from Brain Dead Takes. Confirm your email to join, and unsubscribe from any newsletter.

Email signup and delivery are handled by Brevo. Your address isn’t published. Privacy · Open the signup form directly