Hong Kong's confidence in a 2016 bridge timetable did not hold
“meet the target of commissioning the HZMB Main Bridge in 2016”
BThe context
The announcement acknowledged almost a year's delay from judicial review and proposed recovering time with construction changes and extra resources. It tied Hong Kong facilities to the main bridge's commissioning target, rather than promising every related road would open simultaneously. 1
By May 2015 the official reply to legislators said completing the entire project by end-2016 would be very difficult. The transport secretary's first-day remarks document actual public operation on October 24, 2018. These distinguish an early target, a later warning and the eventual opening. 23
CWhat actually happened
DThe receipts
- 1Hong Kong government: original confidence and recovery planOriginal report · info.gov.hk
- 2Legislative Council reply: timetable pressure acknowledgedOriginal report · info.gov.hk
- 3Transport secretary: first day of bridge operationOutcome evidence · tlb.gov.hk
We quote short excerpts and link to sources. Archived copies and screenshots, when added, are labelled separately from original publications.
EFinal verdict
Prediction Failed